Saturday, February 4, 2017

GODDARD-PARDEE CONSTRUCTION could increase travel time to and from schools

Anyone who travels through the Goddard Road and Pardee intersection on their way to or from school should leave a little more time, beginning this week.

A sewer maintenance project at Pardee and Goddard is scheduled to kickoff on Monday, February 6.

The City of Taylor has contracted with Bidigare Contractors, Inc. to perform a sanitary sewer maintenance project at the southeast corner of Pardee and Goddard.  Mobilization and traffic control was scheduled to begin last Wednesday and the maintenance work is scheduled to begin Monday.  

The project will last approximately three to four weeks.  Work will take place between 7 a.m. and 6 p.m., Mondays through Fridays.

The right lane of northbound Pardee Road from Goddard Road south to Cloverlawn Street will be closed to traffic during the project.  During this period vehicular traffic to Malek Al Kabob, Little Caesars Pizza and Goddard Liquor Store will need to use the Goddard Road entrance.

Pavement removal and sewer maintenance work activities will begin the week of February 6.  Once work is complete, Pardee Road will be temporarily restored to allow normal traffic use.  In the spring, the contractor will return to construct permanent road restoration work.

Trash pick-up will continue on the regularly scheduled days.  Continue to place the trash receptacles at curbside on the opposite side of the street that work is taking place on, or at the center of the street next to a repair area.


The City of Taylor apologizes for any inconvenience this work may cause.  The City and Bidigare will try to limit the inconvenience .  Your cooperation in this matter will be greatly appreciated.  Should you have any questions please contact Greg Mayhew, City Engineer, at (734) 374-1473, or by email at gmayhew@ci.taylor.mi.us.