Anyone
who travels through the Goddard Road and Pardee intersection on their way to or
from school should leave a little more time, beginning this week.
A
sewer maintenance project at Pardee and Goddard is scheduled to kickoff on Monday,
February 6.
The
City of Taylor has contracted with Bidigare Contractors, Inc. to perform a
sanitary sewer maintenance project at the southeast corner of Pardee and
Goddard. Mobilization and traffic control was scheduled to begin last
Wednesday and the maintenance work is scheduled to begin Monday.
The
project will last approximately three to four weeks. Work will take place
between 7 a.m. and 6 p.m., Mondays through Fridays.
The
right lane of northbound Pardee Road from Goddard Road south to Cloverlawn
Street will be closed to traffic during the project. During this period
vehicular traffic to Malek Al Kabob, Little Caesars Pizza and Goddard Liquor
Store will need to use the Goddard Road entrance.
Pavement
removal and sewer maintenance work activities will begin the week of February
6. Once work is complete, Pardee Road will be temporarily restored to
allow normal traffic use. In the spring, the contractor will return to
construct permanent road restoration work.
Trash
pick-up will continue on the regularly scheduled days. Continue to place
the trash receptacles at curbside on the opposite side of the street that work
is taking place on, or at the center of the street next to a repair area.
The
City of Taylor apologizes for any inconvenience this work may cause. The
City and Bidigare will try to limit the inconvenience . Your cooperation
in this matter will be greatly appreciated. Should you have any questions
please contact Greg Mayhew, City Engineer, at (734) 374-1473, or by email at
gmayhew@ci.taylor.mi.us.